|
news
Meaning of reasonable endeavours
In Rhodia International Holdings & Anor v Huntsman International LLC, the High
Court decided that where a party was contractually obliged to use reasonable
 |
|
Jonathan Rands |
endeavours
to obtain a third-party consent, and the contract prescribed certain specific steps
to be taken (in this case, providing a parent-company guarantee to induce the third
party to give consent) the party was obliged to take those steps, even though they
might be detrimental to its own commercial interests. The Court also considered
the difference between the terms "reasonable endeavours" and "best endeavours" and
expressed the view, that the former imposed a less stringent obligation than the
latter.
BACKGROUND
The difference between an obligation to use "best endeavours", or "all reasonable
endeavours", or "reasonable endeavours" to
fulfil an obligation, in the context
of a commercial contract, has been a matter of some debate. The Court of Appeal
has held that a person's obligation to use best endeavours means that he had to
do "all he reasonably can" to obtain the desired result. On the other hand, the
High Court has held that an obligation to use reasonable endeavours, was less stringent
than an obligation to use best endeavours.What actually constitutes "reasonable
endeavours" will vary according to the circumstances of the case, but an obligation
to use reasonable endeavours does not generally require a party to do anything that
would involve sacrificing its own commercial interests.
FACTS
In February 2001, RIH agreed with HIL to sell a chemical manufacturing business
to HIL and/or its designated purchaser, HSS, a special purpose vehicle recently
incorporated by HIL. The relevant terms of the sale agreement were that:
- HIL would procure that HSS carried out and completed specified customer
and supplier contracts and punctually performed and discharged RIH's obligations
under those contracts (clause 14.1)
- Where such a contract contained some restriction on its transferability
(defined as a 'Restricted Contract'), RIH and HIL undertook to use their respective
reasonable endeavours ..... to obtain all requisite consents or agreements of all
parties to each Restricted Contract to whatever assignment, transfer or novation
is necessary to enable [HIL] to perform such Restricted Contract on or after Completion
or, as the case may be, to transfer the benefit and,for the purpose of obtaining
any such consent or agreement, [HIL] shall, if such other party to the Restricted
Contract…so reasonably requires, [HIL], its immediate parent company or one of [HIL]'s
subsidiaries or subsidiary undertakings with sufficient standing and net worth shall
enter into a direct covenant with such other party to perform and observe such Restricted
Contract…from the date of its assignment, novation or transfer in favour of [HIL]."
(clause 15.1.2).
- Until the necessary consents were secured, HIL would procure that HSS,
at its own expense, performed RIH's obligations under the restricted contracts as
RIH's agent, and paid RIH for any liabilities arising as a result of any non-performance
or negligent performance (clause 15.1.3).
- Provided that HIL had performed its obligations under clause 15.1.2,
if any of the restricted contracts could not be transferred to HSS within six months
of the date of completion, then HIL would be entitled by written notice to require
RIH to exclude that contract from the business assets sold under the agreement and
to pay HIL an amount equal to the diminution in value of the business caused by
the exclusion (clause 15.1.4).
One of the assets of the business was a manufacturing plant power for which was
provided by an on-site facility owned and operated by NPL. The energy supply contract
between RIH and NPL provided that RIH could assign, novate or otherwise transfer
its rights under the contract, provided that RIH satisfied NPL that the party to
whom the proposed transfer was made was capable of fulfilling its obligations under
the contract, and that RIH gave at least 90 days' notice of its intention to assign,
novate or otherwise transfer.
Pending novation, HSS undertook to perform RIH's obligations under the energy supply
contract, and in fact did so from March 2001. The first step towards novation was
made by HIL's solicitors, who produced a draft form of novation and sent it to both
RIH and HIL. However, in July 2001, NPL informed RIH by letter that while it was
happy in principle for the novation to proceed, it had
concerns about the financial strength of HSS (which, as a new company,
had yet to file statutory accounts) and that
it was only prepared to novate if it received an acceptable guarantee of HSS's obligations.
NPL provided HIL with a copy of the letter. In October 2001, following a meeting
with NPL, RIH informed HIL that NPL was still insisting on a guarantee.
In January 2002, HIL sent to NPL a file of financial information on HSS, but stated
that it did not guarantee the debts of its subsidiaries. In March 2002, NPL replied
that it could not take the information as a substitute for full accounts and, pending
publication of satisfactory accounts, it still required some sort of guarantee,
bond or letter of credit before it would agree to the novation. In October 2002,
HIL sent NPL a copy of HSS's first statutory accounts, which showed HSS to be financially
weak, and in January 2003 NPL replied that it would not consent to the novation
until HSS posted substantially improved financial results.
There was no further communication between HIL and NPL concerning the novation and
by then HIL was already contemplating closing the plant. In March 2004, HIL gave
RIH notice that it no longer intended to perform RIH's obligations under the energy
supply contract, and also purported to give RIH written notice under clause 15.1.4
of the sale agreement requiring the energy supply contract to be excluded from the
sale.
A
few days later the plant was closed.
- In October 2005, NPL commenced arbitration proceedings against RIH
for unpaid invoices, to a total of £14.8 million, submitted by NPL under the take-or-pay
provisions of the energy supply contract. RIH in turn issued proceedings against
HIL, claiming that HIL had breached its obligations under clause 15.1.2 by not using reasonable endeavours to procure the novation of the energy supply contract, so
that its purported notice under clause 15.1.4 was invalid and it remained liable,
pursuant to clause 15.1.3, to perform RIH's obligations under the energy supply
contract.
DECISION
Although incidental to its decision the High Court also considered the difference
between "reasonable endeavours" and "best endeavours". It concluded that an obligation
to use reasonable endeavours was less stringent than an obligation to use best endeavours.
For example there might be a number of reasonable courses which could be followed
in a given situation to achieve a particular aim, and an obligation to use reasonable
endeavours to achieve the aim probably only required a party to take one reasonable
course, not all of them, whereas an obligation to use best endeavours probably required
a party to take all the reasonable courses it could. In this context, the Court
thought that an obligation to use "all reasonable endeavours" was equivalent to
an obligation to use “best endeavours”. However, the Court found that HIL was in
breach of clause 15.1.2 because although an obligation to use reasonable endeavours
does not usually require a party to sacrifice its commercial interests, where the
contract was, as in this case, very specific as to what ‘reasonable endeavours’
signified in terms of the practical steps to be taken, those steps would have to
be taken, even if it damaged that party's commercial interests.
CONCLUSIONS
- There may be no practical difference between obligations to use ‘best endeavours’
and ‘all reasonable endeavours’.
- An obligation to use ‘reasonable endeavours’ is inferior, in terms of the severity
of the obligation, to an obligation to use ‘best’ or ‘all reasonable’ endeavours.
- There is a definite benefit, when the other contracting party has undertaken to
use endeavour to do something, in specifying in the contract what the other party
must do (in effect, quantifying the endeavours obligation).
Other news
|